Rabai completes construction and commences full commercial operations

Helen Tarnoy appointed as new Managing Director

Rabai succesfully synchronized to the grid.

Completion of Second Round of Corporate Financing

Double award as Project Finance magazine pronounces Rabai 'African Power Deal of the Year' 2008

Rabai awarded PFI 'African Power Deal of the Year' 2008

CEC lists on Lusaka Stock Exchange

Construction of new 90MW diesel power plant in Rabai, Kenya

Aldwych International unconditionally prequalified by Eskom for baseload tender

Kenyan High Court Case Withdrawn

Announcements

October 10th, 2007


Kenyan High Court Case Withdrawn

On 1st March 2007, Simba applied to the High Court of Kenya for a Judicial Review of the hearing conducted by The Public Procurement Complaints, Review and Appeals Board.  This hearing was scheduled for 15th October 2007.  On 5th October 2007 Simba unconditionally withdrew its application to the High Court for a Judicial Review.

While the appeal process has delayed the project somewhat, development is now progressing quickly again and the project should enter construction in the first quarter of 2008.